Federal Energy Regulatory Commission Approves Interconnection Service Agreement
The Federal Energy Regulatory Commission has issued a delegated order approving the Interconnection Service Agreement among PJM Interconnection, L.L.C., Greenwood Solar I, LLC, and Virginia Electric and Power Company. The agreement was submitted on June 11, 2025, and after a public notice period, no protests or adverse comments were filed. The Commission accepted the submittal for filing, effective August 11, 2025. This approval does not constitute approval of any service, rate, or charge, but rather final agency action, which may be subject to rehearing within 30 days.
Key Takeaways:
- The Federal Energy Regulatory Commission has issued a delegated order approving the Interconnection Service Agreement among PJM Interconnection, L.L.C., Greenwood Solar I, LLC, and Virginia Electric and Power Company.
- The agreement was submitted on June 11, 2025, and was publicly noticed before being accepted for filing on August 11, 2025.
- The approval does not constitute approval of any service, rate, or charge, but rather final agency action.
- Requests for rehearing by the Commission may be filed within 30 days of the date of issuance of this order, pursuant to 18 C.F.R. § 385.713.
- The Interconnection Service Agreement is part of the PJM Service Agreements Tariff, specifically PJM SA No. 5561.
- The Director of the Division of Electric Power Regulation - East, Kurt M. Longo, issued the delegated order.
Statistics:
- 30: The number of days within which requests for rehearing by the Commission may be filed, pursuant to 18 C.F.R. § 385.713.
- 18 C.F.R. § 385.713: The relevant Commission regulation allowing for rehearing requests to be filed within 30 days of order issuance.
- August 11, 2025: The effective date of the delegated order approving the Interconnection Service Agreement.
- June 11, 2025: The date on which the agreement was submitted to the Commission.
Sources:
- Federal Energy Regulatory Commission, Washington, DC 20426, Docket No. ER25-2489-000, Issued: August 4, 2025.
- PJM Interconnection, L.L.C., PJM Service Agreements Tariff, PJM SA No. 5561, PJM SA No. 5561 among PJM, Greenwood and Virginia Power (5.0.0).
- 18 C.F.R. § 385.713 (Commission regulation regarding rehearing requests).