The Federal Energy Regulatory Commission has issued a delegated order approving the revised agreement for the Interconnection, Entitlements, Operation, and Maintenance of Facilities between Public Service Company of Colorado (PSCo) and other relevant parties. The agreement, which was filed on May 30, 2025, outlines the terms and conditions for the operation and maintenance of facilities between PSCo and other entities involved. Following the filing, no protests or adverse comments were received by the Commission, and as a result, the submittal was accepted for filing on May 31, 2025.

Key Takeaways:

  • The Federal Energy Regulatory Commission issued a delegated order approving the revised agreement for the Interconnection, Entitlements, Operation, and Maintenance of Facilities between PSCo and other parties on July 25, 2025.
  • The agreement was filed by Public Service Company of Colorado on May 30, 2025, and was accepted for filing on May 31, 2025, without any protests or adverse comments.
  • The Commission's regulations, specifically Rule 214 (18 C.F.R. § 385.214), allowed for notices of intervention, timely filed motions to intervene, and unopposed motions to intervene out-of-time to be granted.
  • The order does not constitute approval of any service, rate, charge, classification, or rule, regulation, contract, or practice affecting such rate or service provided for in the filed documents.
  • The order is without prejudice to any findings or orders which have been or may hereafter be made by the Commission in any proceeding now pending or hereafter instituted by or against applicant(s).
  • The Commission's action constitutes final agency action, and requests for rehearing may be filed within 30 days of the date of issuance of this order.

Statistics:

  • The agreement was filed under Docket No. ER25-2379-000.
  • The Commission's action was issued by Amery S. Pore, Director, Division of Electric Power Regulation - West.
  • The document accession numbers are 20250725-3027 for the Filing Date.
  • The filing date for the document Content(s) ER25-2379-000 DLO.docx is also July 25, 2025.

Sources:

  • FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426 OFFICE OF ENERGY MARKET REGULATION Public Service Company of Colorado Docket No. ER25-2379-000 Issued: July 25, 2025