Federal Energy Regulatory Commission Issues Delegated Order in PJM Interconnection Case

The Federal Energy Regulatory Commission (FERC) has issued a delegated order in the case of PJM Interconnection, L.L.C. (PJM) on June 10, 2025. The commission accepted for filing an amended Wholesale Market Participation Agreement among PJM, ET CAP CA Holdings LLC, and Commonwealth Edison Company, effective June 14, 2025. This action does not constitute approval of any service, rate, or charge, but it does grant notices of intervention and motions to intervene filed by certain parties.

Key Takeaways:

  • The FERC issued a delegated order in the case of PJM Interconnection, L.L.C. on June 10, 2025.
  • The order accepted for filing an amended Wholesale Market Participation Agreement among PJM, ET CAP CA Holdings LLC, and Commonwealth Edison Company, effective June 14, 2025.
  • The filing was publicly noticed, and no protests or adverse comments were filed.
  • The order grants notices of intervention and motions to intervene filed by certain parties.
  • The action does not constitute approval of any service, rate, charge, classification, or any rule, regulation, contract, or practice affecting such rate or service provided in the filed document(s).
  • This order constitutes final agency action.

Statistics:

  • The FERC issued the delegated order on June 10, 2025.
  • The effective date of the order is June 14, 2025.
  • The filing was publicly noticed, and no protests or adverse comments were filed within the established timeframe.
  • The order grants notices of intervention and motions to intervene to certain parties.
  • The action does not constitute approval of any service, rate, charge, classification, or any rule, regulation, contract, or practice affecting such rate or service provided in the filed document(s).
  • The order constitutes final agency action, and requests for rehearing may be filed within 30 days of the date of issuance.

Sources:

  • FERC, Docket No. ER25-1948-000, Issued: June 10, 2025.