Federal Energy Regulatory Commission Issues Delegated Order in Tri-State Generation and Transmission Association Case
On May 21, 2025, the Federal Energy Regulatory Commission (FERC) issued a delegated order in the case of Tri-State Generation and Transmission Association, Inc. (Tri-State) on Docket No. ER25-1792-000. The order was issued by Amery S. Pore, Director, Division of Electric Power Regulation - West. Tri-State had submitted revisions to a Wholesale Electric Service Contract between Tri-State and Poudre Valley Rural Electric Association, Inc. on March 27, 2025, to reflect agreements recently entered into, terminated, or amended by the parties.
Key Takeaways:
- The FERC delegated order was issued on May 21, 2025, in the case of Tri-State Generation and Transmission Association, Inc. on Docket No. ER25-1792-000.
- The order accepted revisions to a Wholesale Electric Service Contract between Tri-State and Poudre Valley Rural Electric Association, Inc. submitted on March 27, 2025.
- The filing was publicly noticed, and no protests or adverse comments were filed.
- The action does not constitute approval of any service, rate, charge, classification, or rule, regulation, contract, or practice affecting such rate or service.
- The order constitutes final agency action, and requests for rehearing may be filed within 30 days of the date of issuance.
- Amery S. Pore, Director, Division of Electric Power Regulation - West, issued the order.
- The filing related to Rate Schedule No. 27, Poudre Valley (6.0.0) and was submitted as part of Document Accession #: 20250521-3106.
Statistics:
- FERC issued the delegated order on May 21, 2025.
- Tri-State submitted revisions to the contractual agreement on March 27, 2025.
- The filing is related to Docket No. ER25-1792-000.
- The order was issued by Amery S. Pore, Director, Division of Electric Power Regulation - West.
- No protests or adverse comments were filed in response to the proposal.
- Requests for rehearing may be filed within 30 days of the date of issuance of this order.
Sources:
- Federal Energy Regulatory Commission, FERC Issues Delegated Order (2025).
- Tri-State Generation and Transmission Association, Inc., Tri-State Wholesale Electric Service Contracts, Rate Schedule No. 27, Rate Schedule No. 27, Poudre Valley (6.0.0), Document Accession #: 20250521-3106.