Federal Energy Regulatory Commission Issues Delegated Order on PJM Interconnection Service Agreement
The Federal Energy Regulatory Commission has issued a delegated order on PJM Interconnection, L.L.C.'s amended Interconnection Service Agreement, which was submitted on March 24, 2025. The submittal was accepted for filing on May 24, 2025, and no protests or adverse comments were filed. This action does not constitute approval of any service, rate, or practice, but rather a final agency action, allowing for rehearing by the Commission within 30 days.
Key Takeaways:
- PJM Interconnection, L.L.C. submitted an amended Interconnection Service Agreement on March 24, 2025.
- The submittal was accepted for filing on May 24, 2025, as requested.
- No protests or adverse comments were filed in response to the public notice.
- The delegated order does not constitute approval of any service, rate, or practice.
- The Commission may rehear the matter within 30 days of the order's issuance.
Statistics:
- The amended Interconnection Service Agreement was submitted on March 24, 2025.
- The filing was publicly noticed.
- No protests or adverse comments were filed.
- The order was issued by Kurt Longo, Director, Division of Electric Power Regulation - East, on May 12, 2025.
- The Commission has 30 days to rehear the matter after the order's issuance.
Sources:
- PJM Interconnection, L.L.C., PJM Service Agreements Tariff, PJM SA No. 3753, PJM SA No. 3753 among PJM, Gavin Power, LLC and Ohio Power (5.0.0).
- Federal Energy Regulatory Commission, Document Accession #: 20250512-3028, Filed Date: 05/12/2025.
Note: The document numbers and accession numbers are direct quotes from the provided text.