Federal Energy Regulatory Commission Requests Additional Information from Gulf South Pipeline Company, LP

The Federal Energy Regulatory Commission has issued a request for additional information from Gulf South Pipeline Company, LP in relation to its certificate application. The request asks for specific data to assist in the analysis of Gulf South's proposal and is in accordance with the Commission's Rules of Practice and Procedure. The information requested includes details on costs associated with reserved capacity, interruptible service rates, and work papers used in deriving interruptible rates. Gulf South is required to respond to the data request within three business days, with all responses to be filed electronically via the eFiling link on the Commission's website.

Key Takeaways:

  • The Federal Energy Regulatory Commission has requested additional information from Gulf South Pipeline Company, LP in relation to its certificate application, specifically to assist in the analysis of the proposal.
  • The request includes two main data points: the costs associated with reserved capacity and the interruptible service rates to be charged for additional capacity made available as a result of the Project.
  • Gulf South is required to respond to the data request within three business days, with all responses to be filed electronically via the eFiling link on the Commission's website.
  • The responses must be filed under oath by an authorized Gulf South representative, with the name, position, and telephone number of the respondent included for each item.
  • Damien Gaul, a representative of the Commission, is available to answer any questions regarding the data request.

Statistics:

  • 59,000 dekatherms per day of existing capacity reserved for the Parks Line Upgrade and Sorrento Station Project.
  • Costs associated with reserved capacity are included in the cost of service for the Project.
  • Gulf South does not provide an interruptible service rate to be charged for interruptible service on the Project capacity.
  • Three business days are provided for Gulf South to respond to the data request.
  • Electronic filing is required, with copies to be served on all parties listed on the official service list.

Sources:

  • Federal Energy Regulatory Commission (FERC) Letter Order dated July 22, 2025, in Docket No. CP25-54-000.