FERC Discusses Cape Cod Canal Pipeline Relocation Project Status

The Federal Energy Regulatory Commission held a pre-filing biweekly conference call on August 5, 2025, to discuss the Cape Cod Canal Pipeline Relocation Project in Massachusetts. The call was attended by representatives from federal, state, and local agencies, as well as Algonquin Gas Transmission, LLC, the project proponent. During the call, Algonquin provided an update on the project's status, citing that they are reviewing comments from FERC, USEPA, and USACE on draft resource reports.

Key Takeaways:

  • Algonquin is reviewing comments from FERC, USEPA, and USACE on draft resource reports, a crucial step in the project's approval process.
  • Phase I cultural surveys, wetland/waterbody surveys, and plant surveys have been completed, with a final round of plant surveys scheduled for late August.
  • Algonquin is preparing the draft applicant-prepared Environmental Assessment (EA) and anticipates filing the FERC 7c application in late September/early October.
  • The project's next call is scheduled for Tuesday, August 19, 2025, to continue discussions on the planned Cape Cod Canal Pipeline Relocation Project.
  • The project relocation is subject to federal, state, and local agency approvals, indicating a collaborative effort between various stakeholders.

Statistics:

  • The project's expected filing date for the FERC 7c application is late September/early October 2025.
  • The next pre-filing biweekly conference call is scheduled for Tuesday, August 19, 2025.
  • The project's cultural surveys, wetland/waterbody surveys, and plant surveys have been completed, with a final round of plant surveys scheduled for late August 2025.

Sources:

  • Docket No. PF25-4
  • Julia Yuan, FERC OEP staff Memoroandum (August 18, 2025)
  • Federal Energy Regulatory Commission (FERC)
  • Algonquin Gas Transmission, LLC
  • SWCA Environmental Consultants