FERC Issues Notice of Schedule for Environmental Assessment for Magnum Gas Storage Project

The Federal Energy Regulatory Commission (FERC) has issued a formal notice outlining the schedule for the preparation of an environmental assessment (EA) for the 2025 Amendment Project, a proposed natural gas storage project in Millard, Juab, and Utah Counties, Utah. The project, submitted by Magnum Gas Storage, LLC, seeks to amend the existing Certificate of Public Convenience and Necessity to modify previously approved facilities and construct new ones, increasing the working gas storage capacity by 20.8 billion cubic feet. The EA will be issued on November 13, 2025, and will be subject to a 30-day comment period. The EA will address concerns raised by two landowners, including impacts to adjacent land use, property rights, and lack of adequate project information.

Key Takeaways:

  • The 2025 Amendment Project, proposed by Magnum Gas Storage, LLC, involves modifying previously approved facilities and constructing new ones, increasing the working gas storage capacity by 20.8 billion cubic feet.
  • The Environmental Assessment (EA) will be issued on November 13, 2025, and will be subject to a 30-day comment period.
  • The EA will address concerns raised by two landowners, including impacts to adjacent land use, property rights, and lack of adequate project information.
  • The Federal Energy Regulatory Commission (FERC) has established a 90-day deadline for federal authorizations and permits necessary for the project.
  • The Commission's Office of Public Participation (OPP) supports public engagement and participation in Commission proceedings.
  • The public can access additional information about the project through the FERC website, the eLibrary link, or by contacting the Office of External Affairs.

Statistics:

  • 20.8 billion cubic feet: Proposed increase in working gas storage capacity.
  • 5.2 billion cubic feet: Capacity each of the two authorized caverns.
  • 6: Number of operational days for the brine disposal pond.
  • 30: Number of days for the comment period for the EA.
  • 90: Number of days for federal authorization decision deadline.
  • 4: Number of landowners who have submitted comments.
  • 2: Number of caverns for which redesign is proposed.
  • 2: Number of pipeline interconnections proposed.

Sources:

  • [1] United States of America Federal Energy Regulatory Commission, "NOTICE OF SCHEDULE FOR THE PREPARATION OF AN ENVIRONMENTAL ASSESSMENT FOR THE 2025 AMENDMENT PROJECT" (June 26, 2025).
  • [2] Office of Public Participation (OPP), FERC. (n.d.). [OPP website]. Retrieved from