Florida Gas Transmission Company's Southeast Texas Project Update: Progress on Compressor Station 6.5 and Infrastructure Development
The Florida Gas Transmission Company, LLC (FGT) has submitted a weekly environmental status report to the Federal Energy Regulatory Commission (FERC) detailing the progress of its Southeast Texas Project. The project involves the construction of a new compressor station (CS 6.5) and the upgrade of existing infrastructure in Calcasieu Parish, Louisiana, and Orange County, Texas.
Key Takeaways:
- The Southeast Texas Project was authorized by Commission Order (190 FERC P 61,166) on March 20, 2025.
- FGT has received all necessary federal authorizations and required approvals for the project.
- Construction status as of August 9, 2025:
+ Clearing & Grading (CS 6.5): 100% complete
+ Clearing & Grading (Orange - Entergy M&R): 100% complete
+ Fabrication (CS 6.5): 100% complete
+ Fabrication (Orange - Entergy M&R): 33% complete
+ Welding (CS 6.5): 88% complete
+ Welding (Orange - Entergy M&R): 56% complete
+ New MLV assemblies / Groundworks: 100% complete
+ Station Suction / Discharge Piping / Backfill (CS 6.5): 0% complete
+ Connection Pipe / Backfill (Orange - Entergy M&R): 5% complete
- FGT has completed its project agreements with contractors and acquired necessary materials.
- Contractor yards are onboarding personnel, and project area site visits are being conducted.
- Orange - Entergy M&R activities: site clearing/grading, installing foundations, matting, pipe fabrication, and miscellaneous construction activities are underway.
- CS 6.5 activities: compressor skid, process gas cooler, utility cooler, inlet filter separator, discharge coalescer, MCC, and exhaust stack installation, matting, rocking, installing pipe supports, receiving materials and equipment, and ECD installation/maintenance are ongoing.
- Gillis-Trunkline M&R activities: fabrication welds, site excavation, electrical work, and pipe coating are progressing.
- FGT anticipates tying-in the project facilities to existing facilities at this location during the next reporting period.
Statistics:
- Progress complete on CS 6.5 clearing and grading: 100%
- FGT has obtained 100% of necessary right-of-way and temporary easements for the project
- Completed contracts with third-party contractors: 100%
- Personnel training and onboarding: ongoing
- Project infrastructure under construction: CS 6.5, Orange - Entergy M&R, and Gillis-Trunkline M&R
- Materials and equipment received: 100%
- Landowner complaints received: 0
- Agency correspondence regarding noncompliance: 0
Sources:
- Florida Gas Transmission Company, LLC. (2025, August 9). Southeast Texas Project Docket No. CP24-510-000 Weekly Environmental Status Report No. 18.
- Federal Energy Regulatory Commission. (2025, March 20). Order 190 FERC P 61,166.