Florida Gas Transmission Company's Southeast Texas Project Update: Progress on Environmental Permits and Construction

Florida Gas Transmission Company, LLC has submitted an update on the Southeast Texas Project to the Federal Energy Regulatory Commission. The project, which includes the construction of a new compressor station and upgrade of existing facilities in Louisiana and Texas, has received all necessary federal authorizations and approvals. As of August 16, 2025, construction is ongoing, with 75% of site excavation and groundwork completed for the new compressor station, and 100% of the necessary right-of-way and temporary easements acquired.

Key Takeaways:

  • The Southeast Texas Project has received all necessary federal authorizations and approvals, including a blanket certificate from the Federal Energy Regulatory Commission.
  • Construction is ongoing, with 75% of site excavation and groundwork completed for the new compressor station.
  • 100% of the necessary right-of-way and temporary easements have been acquired for the project.
  • The company has completed its project agreement with its third-party contractor and acquired the necessary materials for the project facilities.
  • Environmental training for project personnel continues, with no problems or non-compliances reported during the reporting period.
  • Landowner complaints have not been received, and the company has implemented measures to address any potential concerns related to the project's compliance with regulatory requirements.
  • The project's construction is progressing, with ongoing work on fabrication, form-pouring, matting, and pipe fabrication.
  • Representative photos of project construction areas have been provided, showing progress on pipe fabrication, form pouring, and other construction activities.

Statistics:

  • 100% of right-of-way and temporary easements acquired for the project.
  • 75% of site excavation and groundwork completed for the new compressor station.
  • 100% of necessary materials acquired for the project facilities.
  • 100% of construction completed for some project facilities.
  • No problems or non-compliances reported.
  • No landowner complaints received.
  • 63% of welding on the new compressor station completed.

Sources:

  • Florida Gas Transmission Company, LLC. Southeast Texas Project Docket No. CP24-510-000 Weekly Environmental Status Report No. 19. Submitted to the Federal Energy Regulatory Commission on August 20, 2025.
  • Attachment 2: TABLE 1.6-1 Environmental Permits and Approvals. Updated May 8, 2025.
  • Attachment 3: Photographs of Project Construction Areas. Presented for Weekly Report No. 19.