Foxhall Village Housing Project Revival: Delivering Affordable Homes in Blackpool
Blackpool's Foxhall Village scheme, a flagship housing project, has overcome significant challenges, including the original developer's collapse, to deliver high-quality affordable homes. The ambitious project, initially designed to provide 410 homes, has seen a transformation with Blackpool Council taking ownership in 2021 and securing a £2.7m government grant. The development, spanning two sites, aims to rejuvenate the central Blackpool area by removing older, squalid buildings and delivering quality affordable housing. The latest phase will bring the total number of homes built to 348, with a final phase expected to be completed next year.
Key Takeaways:
- The Foxhall Village scheme initially aimed to deliver 410 affordable homes but was delayed after the original developer, Hollinwood Homes, entered administration in October 2019, with 193 homes already built.
- Blackpool Council took ownership of the site in August 2021, facilitated new plans with a £2.7m government grant, and partnered with Tyson Construction to deliver further affordable homes.
- The project comprises two sites, with the next phase set to deliver 67 homes (64 houses and 3 apartments) and a final phase focused on building 88 new homes.
- The development includes a mix of tenure homes, including two, three, and four-bedroom properties, with some homes for sale, shared ownership, and affordable rent.
- Local politician Coun Mark Smith has expressed determination to complete the project, providing a significant number of affordable homes for the community.
- Tyson Construction has committed to a Social Return on Investment of over £500,000, investing in local community projects, apprenticeships, and sponsorships.
- The final phase of Foxhall Village West is expected to be completed in 2026.
Statistics:
- 193 homes initially completed in the Foxhall Village scheme but were halted after the developer's administration.
- A £2.7m government grant facilitated the continuation of the project.
- 67 new homes (64 houses and 3 apartments) are set to be completed as part of the next phase.
- The final phase will deliver 88 new homes, bringing the total built to 348.
- Tyson Construction's Social Return on Investment commitment exceeds £500,000.
- The final phase of Foxhall Village West is scheduled for completion in 2026.
Sources:
- Blackpool Gazette (without available subscription link)
- ImageStore JPI Media UK (https://imagestore.jpimedia.uk/webimg/10962122.jpg)
- ImageStore JPI Media UK (https://imagestore.jpimedia.uk/webimg/10962156.jpg)