Gulf South Pipeline Company Submits Monthly Pre-filing Progress Report for Kosciusko Junction Pipeline Project

The Gulf South Pipeline Company, LLC has submitted a monthly pre-filing progress report to the Federal Energy Regulatory Commission for its proposed Kosciusko Junction Pipeline Project. The report summarizes key activities and milestones achieved from August 1 to August 31, 2025. The project, a joint venture between Gulf South Pipeline Company, LLC and Texas Gas Transmission, LLC, aims to construct a new pipeline in the southeastern United States. A pre-filing conference call was held on August 19, 2025, to discuss the project's environmental document and resource reports. Stakeholders were also updated on the project's progress via a formal letter issued on August 22, 2025.

Key Takeaways:

  • The Gulf South Pipeline Company, LLC submitted a monthly pre-filing progress report to the Federal Energy Regulatory Commission for its proposed Kosciusko Junction Pipeline Project.
  • The project involves the construction of a new pipeline in the southeastern United States, with a joint venture between Gulf South Pipeline Company, LLC and Texas Gas Transmission, LLC.
  • A pre-filing conference call was held on August 19, 2025, to discuss the project's environmental document, Draft Resource Reports, and biological assessment.
  • Stakeholders were informed of the project's progress through a formal letter issued on August 22, 2025.
  • The Applicants have obtained survey permission from 100% of affected landowners.
  • Field surveys for the project route have been completed, and resource reports are being prepared for filing in September.

Statistics:

  • 100% of affected landowners have provided survey permission.
  • The project involves the construction of a new pipeline in the southeastern United States.
  • The pre-filing conference call was held on August 19, 2025.
  • The final resource reports will be filed with the commission in September.

Sources:

  • Gulf South Pipeline Company, LLC. (2025, August 31). Kosciusko Junction Pipeline Project Monthly Pre-filing Progress Report August 1, 2025 - August 31, 2025.
  • Debbie-Anne A. Reese, Secretary Federal Energy Regulatory Commission. (2025, August 31). Re: Gulf South Pipeline Company, LLC Texas Gas Transmission, LLC Kosciusko Junction Pipeline Project Docket No. PF25-6-000 Monthly Pre-filing Progress Report.