India's rapidly growing power transmission network, spanning over 494,000 circuit kilometres of lines and 1.33 million megavolt-amperes of transformation capacity, is struggling to accommodate the increasing deployment of renewable energy. The imbalance between clean power generation and evacuation infrastructure has resulted in a growing gap, limiting renewable integration and increasing the risk of stranded assets and higher delivery costs. A recent report by the Institute for Energy Economics and Financial Analysis highlights the critical challenges facing India's power transmission network and the need for targeted reforms to ensure a resilient and efficient system capable of supporting high renewable penetration.
Key Takeaways:
- The power transmission network in India spans over 494,000 circuit kilometres of lines and 1.33 million megavolt-amperes of transformation capacity, forming a fully synchronised national grid.
- The network struggles to keep up with renewable energy deployment, leading to a growing gap between clean power generation and the availability of evacuation infrastructure.
- The widening gap between planned and actual transmission network expansion is becoming evident, with a 42% shortfall in new transmission lines commissioned in FY2025.
- Up to 71% of ISTS corridors operate below 30% utilisation, underscoring the mismatch between infrastructure availability and actual power flows.
- Structural and procedural bottlenecks, including right-of-way disputes, prolonged land acquisition processes, and multi-agency approval requirements, add to the delay.
- The impact is most visible in Rajasthan, where 8 gigawatts of renewable energy capacity remains stranded, with nearly half curtailed during peak solar hours.
- Over 50GW of renewable energy capacity is currently stranded nationwide, increasing per-unit transmission costs, weakening project viability, and deterring private investment.
- A unified generation-transmission planning framework and a single-window clearance system are essential to streamline approvals and encourage timely commissioning of transmission projects.
Statistics:
- 494,000 circuit kilometres of transmission lines
- 1.33 million megavolt-amperes of transformation capacity
- 42% shortfall in new transmission lines commissioned in FY2025 (8,830ckm vs. 15,253ckm target)
- 71% of ISTS corridors operate below 30% utilisation
- 8 gigawatts of renewable energy capacity stranded in Rajasthan
- Over 50GW of renewable energy capacity currently stranded nationwide