Integrated Energy Data Resource (IEDR) Utility Budget Progress Report 2024
The New York State Public Service Commission has issued a regulatory document on the Integrated Energy Data Resource (IEDR) Utility Budget Progress Report 2024, submitted by Consolidated Edison Company of New York, Inc. (Con Edison) and Orange and Rockland Utilities, Inc. (O&R). The report provides details on the costs incurred by the companies to implement Phase 2 of the IEDR from April 1, 2024, to December 31, 2024. The report highlights the utility coordination group's efforts and IEDR projects and investments.
Key Takeaways:
- The report covers the costs incurred by the Companies to implement Phase 2 of the IEDR from April 1, 2024, to December 31, 2024.
- The Companies participate in the Utility Coordination Group (UCG) established by the New York State Energy Research and Development Authority (NYSERDA) and Commission Staff.
- The UCG has held regular meetings since 2Q 2024, covering topics such as Phase 1 data cleanup, Phase 2 use cases, and data delivery requirements.
- The Companies have participated in six biweekly virtual UCG meetings, five in 3Q 2024, and four in 4Q 2024, covering various topics related to IEDR use cases and platform development.
- The IEDR Program Team and IEDR Development Team have met multiple times for deep-dive sessions on various use cases, including Rate Plan Data and Hosting Capacity Maps.
- The Companies have participated in the IEDR Advisory Group meetings to refine priorities and scope of Phase 2 use-cases.
- The Companies have invested in various projects and initiatives to support the implementation of the IEDR, including people, technology, and process development.
- The Companies have commemorated various milestones and partnerships, such as the Q2 2024 Quarterly report filed on July 30, 2024, and the announcement of the completion of Phase 1 at the end of Q1 2024.
Statistics:
- The report covers a period from April 1, 2024, to December 31, 2024.
- The Companies have participated in a total of 15 biweekly virtual UCG meetings since 2Q 2024.
- The IEDR Program Team and IEDR Development Team have met multiple times for deep-dive sessions on various use cases.
- The Companies have invested in various projects and initiatives to support the implementation of the IEDR.
- The document can be viewed at this link: https://documents.dps.ny.gov/public/common/search.html
Sources:
- Order Approving Integrated Energy Data Resource Phase 2 Budgets (Order)
- Public Service Commission's Order
- New York State Energy Research and Development Authority (NYSERDA)
- Utility Coordination Group (UCG)
- Integrated Energy Data Resource (IEDR)
- Consolidated Edison Company of New York, Inc. (Con Edison)
- Orange and Rockland Utilities, Inc. (O&R)
- IEDR Program Team (Deloitte Consulting, Pecan Street)
- IEDR Development Team (E-source, Utility API, FluxTailor, TRC Companies, and HumanLogic)