Natural Gas Pipeline Company of America LLC Submits Weekly Status Report for Columbus City I/W Well Relocation Project
Natural Gas Pipeline Company of America LLC has submitted a weekly status report to the Federal Energy Regulatory Commission (FERC) for the Columbus City I/W Well Relocation Project. The report covers project-related activities occurring between June 30, 2025, and July 6, 2025. The report provides an update on the construction status of the project, including the work completed and planned for the next reporting period.
Key Takeaways:
- The Natural Gas Pipeline Company of America LLC submitted a weekly status report to the Federal Energy Regulatory Commission (FERC) for the Columbus City I/W Well Relocation Project, covering project-related activities between June 30, 2025, and July 6, 2025.
- The report indicates that Natural's contractor continued demolition and removal at the abandoned well sites, with no work conducted on July 4-6, 2025, due to the Independence Day holiday.
- All erosion control devices were inspected throughout the week and found to be in good, working condition.
- The contractor plans to continue demolition and removal work at the abandoned well sites as well as begin drilling operations for the new wells at the new well site.
- No landowner or resident complaints were received during this reporting period.
- No correspondence from federal, state, or local permitting agencies concerning instances of non-compliance was received.
Statistics:
- Reporting period: June 30, 2025, through July 6, 2025
- Work completed: Demolition and removal at abandoned well sites
- Work planned for the next reporting period: Continue demolition and removal work, begin drilling operations for new wells
- Erosion control devices inspected: 100% (all found to be in good, working condition)
- Landowner or resident complaints: 0 (none reported during this period)
- Correspondence from federal, state, or local permitting agencies: 0 (none received during this period)
Sources:
- Natural Gas Pipeline Company of America LLC, "Weekly Status Report No. 8 for the Columbus City I/W Well Relocation Project," June 30, 2025 - July 6, 2025.
- Federal Energy Regulatory Commission, "Notice of Filing of the Weekly Status Report No. 8 for the Columbus City I/W Well Relocation Project," Docket No. CP25-85-000.