New Wind Farm in Thuringia to Supply 10,500 Households with Renewable Electricity
Construction is set to begin in September 2025 on a new wind farm in Sömmerda, Thuringia, Germany, marking a significant step towards implementing the energy transition in the region. The wind farm, developed by Energiequelle GmbH, will feature four Enercon E-160 wind turbines with a total capacity of over 22 megawatts, capable of supplying renewable electricity to around 10,500 households and saving approximately 27,000 tons of CO2 annually. After a decade-long project development process, the wind farm's construction is expected to commence with foundation work scheduled for May 2026, and the first turbine expected to be commissioned in October 2026.
Key Takeaways:
- The new wind farm in Sömmerda, Thuringia, will be built by Energiequelle GmbH, featuring four Enercon E-160 wind turbines with a total capacity of 22.24 MW (five 5.56 MW turbines).
- The turbines are situated in priority area W-18, designated in the draft of the “Wind Energy” regional development plan for Central Thuringia.
- The wind farm is expected to supply 10,500 households with renewable electricity, saving approximately 27,000 tons of CO2 annually.
- Construction is scheduled to begin in September 2025, with foundation work planned for May 2026 and the first turbine expected to be commissioned in October 2026.
- The project marks an important step towards implementing the energy transition in the region and supports sustainable development.
- Energiequelle is planning several additional wind farms in Thuringia, with three permits totaling 66 MW already granted and another 150 MW in the pipeline.
- Jürgen Fuß, Project Developer at Energiequelle, emphasized the significance of the project, stating that, "The start of construction marks an important milestone for us and the region. The energy transition is becoming tangible here, and we’re excited to finally get started after such a long planning period."
Statistics:
- Total capacity of the wind farm: 22.24 MW (four 5.56 MW turbines x 4)
- Number of households expected to be supplied with renewable electricity: 10,500
- Annual CO2 savings: approximately 27,000 tons
- Construction start date: September 2025
- Foundation work schedule: May 2026
- Commissioning of the first turbine: October 2026