Pacific Gas and Electric Company has submitted a request to the Federal Energy Regulatory Commission for an extension of time to submit design plans for a log boom at Kidd Lake Dam, part of the Drum-Spaulding Hydroelectric Project. The original submission deadline was July 31, 2023, and the company is seeking additional time to complete the installation documents. The request includes a reasoned basis for the delay, as required by Title 18 of the Code of Federal Regulations, Section 12.40(d).

Key Takeaways:

  • Pacific Gas and Electric Company has submitted a request for an extension of time to submit design plans for a log boom at Kidd Lake Dam.
  • The original submission deadline was July 31, 2023, and the company is seeking additional time to complete the installation documents.
  • The extension of time request includes a reasoned basis for the delay, as required by Title 18 of the Code of Federal Regulations, Section 12.40(d).
  • The request is related to the Drum-Spaulding Hydroelectric Project, Federal Energy Regulatory Commission (FERC) No. 2310.
  • PG&E has designated Lacy Cannon, dam safety engineer, as a contact for technical questions at (530) 205-5404, and Jackie Pope, license coordinator, as a contact for general questions at (530) 254-4007.

Statistics:

  • Original submission deadline: July 31, 2023
  • Date of extension request: August 26, 2025
  • Method of submission: Via Electronic Submittal (E-File)
  • Contact information:

+ Lacy Cannon, dam safety engineer: (530) 205-5404

+ Jackie Pope, license coordinator: (530) 254-4007

Sources:

  • Pacific Gas and Electric Company (August 26, 2025): Power Generation 300 Lakeside Drive Oakland, CA 94612 Mailing Address: P.O. Box 28209 Oakland, CA 94604
  • Federal Energy Regulatory Commission (FERC) Regulations: Title 18 of the Code of Federal Regulations, Section 12.40(d)