Pacific Gas and Electric Company Requests FERC Authorization to Replace McCloud Dam Debris Boom

The Pacific Gas and Electric Company (PG&E) has submitted a document to the Federal Energy Regulatory Commission (FERC) requesting construction authorization to replace the debris boom at McCloud Dam, part of PG&E's McCloud-Pit Hydroelectric Project. The request comes after an engineering inspection and evaluation found the boom to be in poor condition, necessitating replacement. PG&E has provided a comprehensive project package, including a work plan, design criteria memorandum, design calculations, design drawings, and specifications, prepared by Black & Veatch and dated July 7th, 2025. The project is scheduled to be released to construction on June 29th, 2026, with a final construction report to be submitted within 90 days of completion.

Key Takeaways:

  • PG&E has submitted a construction authorization request to FERC to replace the debris boom at McCloud Dam, part of the McCloud-Pit Hydroelectric Project.
  • The boom's poor condition was discovered during an engineering inspection and evaluation on July 19th, 2022.
  • The inspection and evaluation recommended that a short-term repair be made to the boom-to-boom connections to increase the working load.
  • The project package includes a Project Work Plan, Design Criteria Memorandum, Design Calculations, Design Drawings, and Specifications, all prepared by Black & Veatch and dated July 7th, 2025.
  • PG&E plans to release the project to construction on June 29th, 2026, with a final construction report to be submitted within 90 days of completion.
  • PG&E will provide updates on the project status and a plan and schedule for further action by November 8th, 2026, if the final construction report is not submitted.

Statistics:

  • The McCloud Dam debris boom was found to be in poor condition after an engineering inspection and evaluation on July 19th, 2022.
  • The boom-to-boom connections were recommended to be short-term repaired to increase the working load.
  • The project package was prepared by Black & Veatch and dated July 7th, 2025.
  • The project is scheduled to be released to construction on June 29th, 2026.
  • PG&E will submit a final construction report within 90 days of project completion.