PJM Interconnection Cancels Service Agreement with Holtwood Solar LLC

PJM Interconnection, L.L.C. has submitted a notice to the Federal Energy Regulatory Commission to cancel the Interconnection Service Agreement (ISA) with Holtwood Solar LLC, effective November 10, 2025, due to Holtwood Solar's decision to withdraw from the queue and not participate in PJM's markets. This cancellation follows the filing of the Holtwood Solar ISA in Docket No. ER22-2242-000 on August 19, 2022. The notice also requests a waiver of Commission Rule 203(b)(3) to include each named person on the official service list.

Key Takeaways:

  • PJM Interconnection, L.L.C. has submitted a notice to cancel the Interconnection Service Agreement (ISA) with Holtwood Solar LLC, effective November 10, 2025.
  • The cancellation is due to Holtwood Solar's decision to withdraw from the queue and not participate in PJM's markets.
  • The Holtwood Solar ISA was filed with and accepted by the Federal Energy Regulatory Commission in Docket No. ER22-2242-000 on August 19, 2022.
  • The notice requests a waiver of Commission Rule 203(b)(3) to include each named person on the official service list.
  • Craig Glazer, Vice President-Federal Government Policy at PJM Interconnection, L.L.C., has been designated as the point of contact for correspondence and communications related to this matter.
  • The cancellation will be reported in PJM's Electronic Quarterly Report (EQR).

Statistics:

  • November 10, 2025: Effective date of the cancellation of Service Agreement No. 5961.
  • 61 days: Timeframe for the cancellation notice, in accordance with section 35.15 of the Commission's regulations.
  • 18 C.F.R. SS 35.15 (2020): Commission regulation governing the notification period for cancellations.
  • 1: Number of companion executed Interconnection Construction Service Agreement submitted for filing.

Sources:

  • PJM Interconnection, L.L.C., Letter Order, Docket No. ER22-2242-000 (Aug 19, 2022).
  • 18 C.F.R. SS 35.15 (2020).
  • Revised Public Utility Filing Requirements, Order No. 2001, 2001-2005 FERC Stats. & Regs., Regs. Preambles P 31,127 at P 249.