RD Bailey Lock and Dam Hydroelectric Project: Annual Progress Report
Rye Development has submitted a preliminary permit annual report to the Federal Energy Regulatory Commission (FERC) regarding the RD Bailey Lock and Dam Hydroelectric Project. The project, issued a preliminary permit on October 3, 2022, is located in Mingo and Wyoming Counties, West Virginia. As a condition of permit issuance, Rye Development is required to submit progress reports every 12 months, which will include an update on project activities and outreach efforts.
Key Takeaways:
- The RD Bailey Lock and Dam Hydroelectric Project is a hydroelectric project located in Mingo and Wyoming Counties, West Virginia, which was issued a preliminary permit by FERC on October 3, 2022.
- The project is managed by Rye Development on behalf of the permittee, Rye Bailey Hydroelectric, LLC, which is responsible for preparing a Pre-Application Document and initiating outreach with state and federal resource agencies, local municipalities, and other stakeholders.
- The project aims to identify resource information and issues, with the permittee responsible for preparing a Pre-Application Document for the Project.
- The permittee can be contacted for any questions or additional information regarding the proposed project through Michael Rooney at (412) 400-4186 or via email at michael@ryedevelopment.com.
Statistics:
- The project is located in Mingo and Wyoming Counties, West Virginia.
- The project was issued a preliminary permit by FERC on October 3, 2022.
- The permittee is required to submit progress reports every 12 months as a condition of permit issuance.
- The project will involve outreach with state and federal resource agencies, local municipalities, and other stakeholders to identify resource information and issues.
Sources:
- Electronically Filed: 1455 SW Broadway, Suite 290, Portland, OR 97201, September 25, 2025, via e-filing to Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street, N.E., Washington, DC 20426.
- Rye Development to Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, Subject: RD Bailey Lock and Dam Hydroelectric Project, FERC Project No. 15277 2025 Preliminary Permit Annual Report.