Renewable World Energies Submits Weekly Filing Regarding Au Train Hydroelectric Project
Renewable World Energies, LLC has submitted a report to the Federal Energy Regulatory Commission (FERC) containing daily emails regarding the Au Train hydroelectric project water levels. The report is in response to FERC's directive on January 11, 2024, to provide daily emails regarding the project's water levels. The emails cover the period from June 30 to July 6 and include detailed information on turbine operations, headwater and tailwater elevations, and flow releases through the powerhouse and siphon.
Key Takeaways:
- Renewable World Energies, LLC submitted a report to FERC containing daily emails regarding the Au Train hydroelectric project water levels.
- The report includes emails sent to D2SI-CRO from June 30 to July 6, as per FERC's directive on January 11, 2024.
- The emails provide detailed information on turbine operations, including unit #1 and unit #2 operating at 100% capacity.
- Headwater and tailwater elevations are also reported, with pond levels on July 5 at 774.90 NAVD88.
- Flow releases through the powerhouse and siphon are recorded, with unit #1 and unit #2 releasing 46 CFS each.
- Precipitation data is included, with no precipitation recorded on July 4.
- The siphon is reported to have been started, operating below 774.0 Local Datum and 775.40 NAVD88.
Statistics:
- 7 daily emails were submitted to FERC covering the period from June 30 to July 6.
- 46 CFS was the flow release through the powerhouse and siphon for both unit #1 and unit #2 on each of the reported days.
- 0 precipitation was recorded on July 4.
- 7. prompt responses were made by Brian Kreuscher, regarding the daily emails being sent to D2SI-CRO.
Sources:
- Federal Energy Regulatory Commission (FERC) directive on January 11, 2024.
- Renewable World Energies, LLC submission to FERC (dated July 2025).
- Emails sent to D2SI-CRO from June 30 to July 6.