Revised Quality Control Inspection Program for Anderson Dam Tunnel Project
Santa Clara Valley Water District has submitted revisions to the Federal Energy Regulatory Commission (FERC) for the Anderson Dam Tunnel Project's Quality Control Inspection Program (QCIP). The updated QCIP Version 7, submitted on September 17, 2024, reflects changes in the project's organization and personnel. Notably, Michel Jubran has been replaced by Rodolfo Ruiz Gaekel as the Resident Engineer, as detailed in a July 30, 2025, email approval from FERC Engineer Fenggang Ma. These revisions have been formally filed with the commission, and any questions can be directed to Ryan McCarter at (408) 630-2983.
Key Takeaways:
- The Anderson Dam Tunnel Project's QCIP Version 7 has been updated to reflect a change in the project's Resident Engineer, with Rodolfo Ruiz Gaekel replacing Michel Jubran.
- The revised ADTP QCIP Construction Management Organization Chart, dated July 18, 2025, has been included as an enclosure to the FERC filing.
- The revisions were approved by FERC Engineer Fenggang Ma via an email on July 30, 2025.
- The updated QCIP Version 7 was officially submitted by Santa Clara Valley Water District to FERC on September 17, 2024.
- The filing includes a resume for Rodolfo Gaekel, the new Resident Engineer, as an enclosure.
Statistics:
- The revised ADTP QCIP Construction Management Organization Chart was updated as of July 18, 2025.
- The QCIP Version 7 revisions were approved by FERC Engineer Fenggang Ma on July 30, 2025.
- The updated QCIP Version 7 was submitted to FERC on September 17, 2024.
Sources:
- Santa Clara Valley Water District
- Federal Energy Regulatory Commission (FERC) Reference: P-5737-CA
- Email from FERC Engineer Fenggang Ma, dated July 30, 2025