Rover Pipeline LLC Submits Biweekly Construction and Environmental Status Report for Sunny Farms Receipt and Delivery Meter Station Project

As of September 15, 2025, Rover Pipeline LLC has submitted a biweekly construction and environmental status report to the Federal Energy Regulatory Commission (FERC) for the Sunny Farms Receipt and Delivery Meter Station Project. The report provides an update on the project's permitting status, construction progress, and plans for the next period. The project, which commenced construction on August 11, 2025, is expected to be completed by September 2025.

Key Takeaways:

  • The project has received all necessary federal and state authorizations to commence construction activities within authorized workspaces.
  • As of September 15, 2025, the project has achieved 100% mobilization, ECD installation, welding, hot tap, civil installation, major equipment installation, instrumentation & electrical, hydro-test, final field fabrication, bolt-up, and painting completion.
  • The remaining activities for the next period include completing fence installation and final site restoration.
  • There have been no non-compliance reports or landowner complaints received by Rover during this reporting period.
  • The project commenced construction on August 11, 2025, and is expected to be completed by September 2025.
  • The report was submitted electronically to the Commission's eFiling website pursuant to Order No. 703, Filing via the Internet Guidelines, issued on November 15, 2007.
  • Total personnel trained to date: 16.

Statistics:

  • 100% mobilization achieved as of September 15, 2025.
  • 100% ECD installation, welding, hot tap, civil installation, major equipment installation, instrumentation & electrical, hydro-test, final field fabrication, bolt-up, and painting completion as of September 15, 2025.
  • 0% completion of fence installation as of September 15, 2025.
  • 90% final restoration completion as of September 15, 2025.
  • 16 total personnel trained to date.

Sources:

  • Federal Energy Regulatory Commission (FERC) Order Issuing Certificate for the Rover Pipeline LLC's Interconnection Project, June 26, 2025.
  • Rover Pipeline LLC's Implementation Plan filed with the Commission on July 2, 2025.
  • FERC Environmental Assessment issued January 24, 2025.
  • Rover Pipeline LLC's Biweekly Construction and Environmental Status Report for the period ending September 15, 2025.
  • Order No. 703, Filing via the Internet Guidelines, issued on November 15, 2007.