Rover Pipeline LLC Submits Biweekly Construction and Environmental Status Report for Sunny Farms Receipt and Delivery Meter Station Project
As of October 14, 2025, Rover Pipeline LLC has submitted its fifth biweekly construction and environmental status report for the Sunny Farms Receipt and Delivery Meter Station Project. In compliance with Environmental Condition No. 8 under the Appendix to the FERC Order, the report details the project's permitting status, construction progress, and plans for the next reporting period.
Key Takeaways:
- The project has received all necessary federal and state authorizations to commence construction activities within all authorized workspaces.
- As of October 14, 2025, 100% of the following activities have been completed: mobilization, ECD installation, welding, hot tap, civil installation, major equipment installation, instrumentation & electrical, hydro-test, and final field fabrication, bolt-up, and painting.
- Fencing is 80% complete, and final restoration is 90% complete.
- The contractor, VRNG Seneca, LLC, will complete the remaining activities during October 2025, including the completion of fence installation and final site restoration.
- No non-compliance reports were received by Rover during this reporting period.
- No landowner or resident complaints were received during this reporting period.
- The project does not impact any streams or environmentally sensitive areas.
Statistics:
- 100% of mobilization has been completed as of October 14, 2025.
- 100% of ECD installation, welding, hot tap, civil installation, major equipment installation, instrumentation & electrical, hydro-test, final field fabrication, bolt-up, and painting have been completed as of October 14, 2025.
- Fencing is 80% complete as of October 14, 2025.
- Final restoration is 90% complete as of October 14, 2025.
- No non-compliance reports were received during this reporting period.
- No landowner or resident complaints were received during this reporting period.
Sources:
- Federal Energy Regulatory Commission (FERC)
- Rover Pipeline LLC
- Federal Energy Regulatory Commission Order No. CP24-508-000 (July 18, 2025)
- FERC Environmental Assessment (January 24, 2025)
- Implementation Plan (filed with FERC on July 2, 2025)
- Order Issuing Certificate (FERC, June 26, 2025)
- FERC Docket No. CP24-508-000
- Rover Pipeline LLC FERC Docket No. CP24-508-000 SUNNY FARMS RECEIPT AND DELIVERY METER STATION PROJECT Biweekly Construction and Environmental Status Report For the Period Ending October 14, 2025