STRABAG Romania Completes Major Milestone in Deleni Wind Farm Project

STRABAG Romania, a subsidiary of the European-based technology group for construction services STRABAG SE, has completed extensive civil, infrastructure, and electrical works for the Deleni Wind Farm Project, a major milestone in the project's development. The wind farm, with a total installed capacity of 140 MW, is expected to generate 370 GWh of green energy annually, powering around 62,000 households and reducing CO2 emissions by an estimated 215,000 tonnes per year. This project marks a significant step towards the sustainable energy transition, aligning with STRABAG's strategic focus on the energy sector.

Key Takeaways:

  • The Deleni Wind Farm Project, with a total installed capacity of 140 MW, is the largest renewable energy plant in the Moldova region and one of the most significant projects of its kind in Romania.
  • The project, commissioned by PPC Renewables Romania, involves the installation of 23 GE Vernova wind turbines, each with a capacity of 6.1 MW, and the construction of four substations with 110 kilometres of medium-voltage cabling.
  • STRABAG Romania completed extensive civil, infrastructure, and electrical works, including the construction of 23 turbine foundations, over 36 kilometres of access roads, and comprehensive drainage systems.
  • The project is expected to generate 370 GWh of green energy annually, powering around 62,000 households and reducing CO2 emissions by an estimated 215,000 tonnes per year.
  • The project diversifies Romania's wind energy production beyond the Dobrogea region, contributing to greater grid stability and energy security.
  • The project brings direct benefits to the local communities in Deleni, Costești, and Bogdănești through job creation, infrastructure upgrades, and long-term tax revenues.

Statistics:

  • The Deleni Wind Farm Project has a total installed capacity of 140 MW.
  • The project involves the installation of 23 GE Vernova wind turbines, each with a capacity of 6.1 MW.
  • The construction of the project includes over 36 kilometres of access roads and comprehensive drainage systems.
  • The project is expected to generate 370 GWh of green energy annually.
  • The project is expected to reduce CO2 emissions by an estimated 215,000 tonnes per year.
  • The project has created direct benefits to local communities through job creation, infrastructure upgrades, and long-term tax revenues.