Tacoma Hydroelectric Project Annual Consultation Meeting Summary

The annual consultation meeting between Public Service Company of Colorado (PSCo) and the US Forest Service (USFS) for the Tacoma Hydroelectric Project was held on May 13, 2024, in a virtual format. The purpose of the meeting was to discuss measures needed to ensure protection and development of the natural resource values of the project area. The meeting summary highlights the key discussions and updates on various projects and initiatives related to the Tacoma Hydroelectric Project.

Key Takeaways:

  • The annual consultation meeting was held with the USFS on May 13, 2024, in a virtual format, as required by USFS Condition No. 4 in the license.
  • The meeting objective was to consider resource protection measures and update the USFS on upcoming projects, as well as share general updates on the Tacoma Hydroelectric Project.
  • Personnel in attendance included Christine Johnston, Art Steimer, Chad Campbell, Don Lopez, Kris Fox from PSCo, and Kenar Houghton, Erin Christenson, Eric Herchmer, Clay Kampf, Cody Jones, and Nick Glidden from the USFS.
  • The meeting discussed the 2025 flume repairs, which will continue this summer to replace supports in the high-priority area near the meadow (staging) area, also known as the smaller trestle area.
  • The project updates included the 2025 flume repairs, landslide concerns, historic properties repairs, and debris cleanup efforts.
  • The meeting also discussed special use permits, including the forebay road, NFSR 783, and the Elbert Creek gaging station.
  • Christine reported that an extension of time was requested from FERC to complete the weed surveys, which was granted, and the survey is intended to be completed as soon as weather and growing conditions allow.

Statistics:

  • 80-130 cfs of water flow has been diverted into the flume since Friday (as reported by Art Steimer).
  • One unit is operating, and the second unit may come online (as reported by Art Steimer).
  • 30 flume supports were replaced last year.
  • A new SUP permit was submitted for the 2025 flume repairs.
  • Garney Construction will perform the 2025 flume repairs.
  • The FOREBAY ROAD application is still in progress.
  • A small drift in the spring may be cleared so a grizzly can drive the full length.

Sources:

  • Public Service Company of Colorado, Tacoma Hydroelectric Project - FERC License (FERC No. 12589)
  • Public Service Company of Colorado, FERC Environment Inspection Report
  • Public Service Company of Colorado, Usfs-Meeting Summary 2024-May 13