Taipower's Maanshan Nuclear Power Plant Unit 2, with an installed capacity of 0.951 GW, has completed its 40-year operating license. As part of the gradual decommissioning of nuclear units, the unit began load reduction at 1:00 p.m. and was safely shut down by midnight. The plant, which accounted for approximately 3% of Taiwan's total power generation, had generated a cumulative total of about 274,160 GWh of electricity over its service period. Taipower has proactively implemented renovation and expansion projects since 2017 to focus on low-carbon, low-emission gas-fired combined-cycle units, while prioritizing the development of dry storage facilities and final disposal sites for nuclear waste.
Key Takeaways:
- Taipower's Maanshan Nuclear Power Plant Unit 2, with an installed capacity of 0.951 GW, has reached the end of its 40-year operating license, accounting for about 3% of Taiwan's total power generation.
- The unit began load reduction at 1:00 p.m. and was safely shut down by midnight, marking the end of its operational life.
- Taipower has implemented renovation and expansion projects since 2017, focusing on low-carbon, low-emission gas-fired combined-cycle units to reduce air pollution and carbon emissions.
- The company plans to develop dry storage facilities and advance site selection and construction of final disposal sites for nuclear waste.
- Taipower's power dispatch strategy includes the accelerated deployment of renewable energy, pumped-storage hydropower, battery storage, and demand-side management to ensure stable electricity supply and reduce emissions.
- Four large gas-fired units with a combined capacity of nearly 5 GW will come online this year, alongside approximately 3.5 GW of new wind and photovoltaic power.
- The upcoming additions will ensure reliable and sufficient power supply for the public.
Statistics:
- The Maanshan Nuclear Power Plant Unit 2 had an installed capacity of 0.951 GW.
- The plant accounted for approximately 3% of Taiwan's total power generation.
- The unit generated a cumulative total of about 274,160 GWh of electricity over its 40-year service period.
- Four large gas-fired units with a combined capacity of nearly 5 GW will come online this year.
- Approximately 3.5 GW of new wind and photovoltaic power will be added to the grid this year.
Sources:
- Republic of China Taiwan Today (May 17), Unit 2 of Taipower's Maanshan Nuclear Power Plant reached the end of its 40-year operating license.
- Taipower spokesperson, Vice President Chih-Meng Tsai.
- Director of Nuclear Power Generation Department, Chih-Pao Lin.
- Director of Power Dispatch Department, Fang-Cheng Chou.
- Director of Nuclear Backend Management Department, Ying-Chen Liao.