The Tennessee Customer Group, comprised of numerous gas distribution systems and municipalities, has filed a joint and several motion to intervene in a Federal Energy Regulatory Commission (FERC) hearing regarding the proposed Mississippi Crossing Project, a $1.7 billion pipeline expansion in Mississippi and Alabama. The group, led by the Municipal Gas Authority of Mississippi, seeks to represent the interests of firm transportation and storage customers of Tennessee Gas Pipeline Company, which stands to be impacted by the project's construction and rates. The FERC hearing, initiated by Tennessee Gas Pipeline Company's abbreviated application, aims to determine the public convenience and necessity of the project.
Key Takeaways:
- The Tennessee Customer Group, consisting of 25 entities, seeks to intervene in the FERC hearing on the Mississippi Crossing Project.
- The group, led by the Municipal Gas Authority of Mississippi, represents the interests of firm transportation and storage customers of Tennessee Gas Pipeline Company.
- The proposed project would create approximately 3.2.1 billion cubic feet per day of incremental firm transportation capacity.
- The project's estimated cost is $1.7 billion, and Tennessee Gas Pipeline Company proposes establishing a new rate zone for the project.
- The FERC deadline for interventions is August 5, 2025, and the Commission must issue a certificate order no later than July 1, 2026.
- The project's timeline includes construction to begin as early as January 1, 2027, and placement in service by November 1, 2028.
- The Tennessee Customer Group's motion to intervene is timely, as the FERC notice of filing establishes that any intervention must be submitted by August 5, 2025.
Statistics:
- The proposed Mississippi Crossing Project would create approximately 3.2.1 billion cubic feet per day of incremental firm transportation capacity.
- The project's estimated cost is $1.7 billion.
- The FERC deadline for interventions is August 5, 2025.
- The Commission must issue a certificate order no later than July 1, 2026.
- Construction of the project could begin as early as January 1, 2027.
- The project is expected to be placed in service by November 1, 2028.
Sources:
- Tennessee Gas Pipeline Company, L.L.C., Docket No. CP25-514-000, Joint and Several Motion to Intervene of City of Bolivar; CenterPoint Energy Resources Corp.; City of Clarksville Gas and Water Department, City of Clarksville; City of Corinth Public Utilities Commission; Delta Natural Gas Company, Inc.; Greater Dickson Gas Authority; Hardeeman Fayette Utility District; Henderson Utility Department; Holly Springs Utility Department; Humphreys County Utility District; Town of Linden; Morehead Utility Plant Board; Portland Natural Gas System, City of Portland; Savannah Utilities; Springfield Gas System, City of Springfield; City of Waynesboro; West Tennessee Public Utility District; Athens Utilities; City of Florence, Alabama; Hartselle Utilities; City of Huntsville, Alabama; Municipal Gas Authority of Mississippi; North Alabama Gas District; Tuscumbia Utilities; and Sheffield Utilities.
- Federal Energy Regulatory Commission (FERC).