Transcontinental Gas Pipe Line Company Submits Biweekly Construction Status Report for Commonwealth Energy Connector Project

The Transcontinental Gas Pipe Line Company, LLC has submitted a biweekly construction status report to the Federal Energy Regulatory Commission (FERC) for the Commonwealth Energy Connector Project, as required by Environmental Condition No. 8. The report covers the period from June 2, 2025, through June 15, 2025, and provides an update on the project's construction status.

Key Takeaways:

  • The Transcontinental Gas Pipe Line Company has acquired all applicable federal authorizations for the project and received Notice to Proceed from FERC on May 1, 2024.
  • Construction commenced on September 5, 2024, and has made significant progress, with the Virginia Station component reaching 89.0% completion.
  • The project's construction status is summarized in the attached table, which highlights the progress of various project components, including the A South Virginia Lateral (SVL) B and the Emporia Meter Station.
  • No problem areas or non-compliance issues were identified during the reporting period, and no corrective actions were implemented.
  • The project has completed all applicable federal authorizations, and transco will continue to monitor for post-construction restoration issues during this post-construction phase of the project.
  • The company will continue to provide biweekly construction status reports to FERC as required by Environmental Condition No. 8.

Statistics:

  • 89.0%: Completion percentage of the Virginia Station component.
  • 100.0%: Completion percentage of the A South Virginia Lateral (SVL) B component.
  • 4.0%: Completion percentage of the Emporia Meter Station component.
  • May 1, 2024: Date FERC issued Notice to Proceed.
  • September 5, 2024: Date construction commenced.
  • June 2, 2025 — June 15, 2025: Reporting period for this biweekly construction status report.