Vermont Public Utility Commission Approves Sheffield Highgate Export Interface Mitigation Fee Allocation
The Vermont Public Utility Commission has approved the proposed allocation of the Sheffield Highgate Export Interface (SHEI) mitigation fee, totaling $10,914.00, among affected utilities to mitigate negative impacts caused by the facility's construction in the SHEI. The commission's decision is based on a proposal submitted by Vermont Electric Cooperative, Inc. (VEC) and supported by the Department of Public Service, Green Mountain Power Corporation, and other stakeholders. The allocation breakdown is as follows: Green Mountain Power (GMP) will receive 60.7%, WEC will receive 3.7%, VEC will receive 28.7%, and municipal utilities will receive 6.9% of the total fee.
Key Takeaways:
- The Vermont Public Utility Commission approved the proposed allocation of the SHEI mitigation fee, totaling $10,914.00, among affected utilities.
- The allocation breakdown is as follows: GMP (60.7%), WEC (3.7%), VEC (28.7%), and municipal utilities (6.9%).
- The allocation is consistent with the methodology approved in previous cases (Case Nos. 17-2869-NMP, 18-0107-NMP, 18-0138-NMP, and 18-2168-NMP).
- The commission conditioned its approval on the municipal utility payment being distributed equitably among the municipal utilities.
- The proposed allocation was supported by the Department of Public Service, Green Mountain Power Corporation, and other stakeholders.
- The SHEI is an area in northern Vermont, including most of the Northeast Kingdom, with existing constraints that have resulted in financial harm to Vermont utilities and customers.
Statistics:
- The total SHEI mitigation fee allocated is $10,914.00.
- The allocation breakdown is: GMP ($6,624), VEC ($3,136), WEC ($401), and municipal utilities ($753).
- The municipal utilities' allocation is 6.9% of the total fee.
- The commission approved the allocation conditioned on the municipal utility payment being distributed equitably among the municipal utilities.
- The SHEI mitigation fee was paid on January 20, 2023, and the proposed allocation was filed on May 9, 2023.
Sources:
- Petition of Concrete Foundation, Inc., Case No. 22-2277-NMP, Order of 9/2/22
- Application of Derby GLC Solar, LLC, Case No. 17-1247-NMP, Order of 1/24/19 at 1
- Case Nos. 17-2869-NMP, 18-0107-NMP, 18-0138-NMP, and 18-2168-NMP, Order of 2/9/22
- Letter from Katie L. Orost, VEC, to Holly Anderson, Clerk of the Commission, dated May 9, 2023 ("VEC Letter")